Energy industry

The Power Station Vasilikos was severely damaged in 2011 following the effects of a forest fire and consequent explosion of ammunition stored directly adjacent to the Power Station at the Military Facility Port. Novmar received the Contract to rebuild and modernize the Boilers 1 and 2. The work scope included repair work and rebuilding to the boilers, the associated equipment, the steel work associated with the components, the ventilation and exhaust ducts and insulation.

Replacement of various ECO-packages during the boiler stop-out. The old, heavily corroded elements were dismantled with the help of a frame specially designed for the project execution.

General contractor of the mechanical assembly of the elements for the biomass boiler, the accessories  and pipe installation.